Table 2

Transaction Pairs by Distance, Project Phase, and Project Type

VariableFloodplain RestorationImprove Fish and Wildlife HabitatMitigate Storm Water RunoffWetland RestorationRemove Invasives and Revegetate
0 to 0.25 km Distance
Preproject phase (–3 to –1 years)128218431231,052
Project phase (0 to 2 years)85229778809931
Postproject phase (3 to 5 years)6424233134815
Mature phase (6+ years)5428527161753
0.25 to 0.5 km Distance
Preproject phase2896581033082,280
Project phase2047261,8301,9522,074
Postproject phase145711933101,770
Mature phase106773614181,686
0.5 to 1 km Distance
Preproject phase1,0062,4093561,3015,830
Project phase8012,4365,6965,8085,320
Postproject phase6322,3592171,0764,497
Mature phase5112,2411341,4434,145